Order Validation


The Order Validation Phase (Vt) is starting with an order and ends with the launch of the manufacturing phase (mt). It covers all necessary activities to confirm and validate completeness of the project detailed technical data not available at time of contract signature. The Order Validation phase should be documented by an annex to the contract (listing missing data) to be signed-up by supplier and customer.

The contractual delivery time can be impacted if the validation time exceeds the duration agreed in the contract.


Standard Sizing Data Certificate shall contain:

  1. Reference (Name or Number of the object)
  2. Layout
  3. Product
  4. Package materials
  5. Packaging matrix
  6. Machine scope
  7. Utilities and Media