Factory Acceptance


The “Factory Acceptance Test” is an optional phase starting at the end of the manufacturing phase. It intends to jointly verify, between Customer and Supplier, the respect of the design data as defined in the “contract” and/or in the “Sizing Data Report”

The verification, if specified in the contract, will be documented by a “Factory Acceptance Test Report”.

The equipment will be dismantled and prepared for shipment after the Manufacturing phase or when the “Factory Acceptance Test Report” is signed by the Customer, when applicable.


 

mime file icon  ABMI Standard Factory Acceptance Test Certificate Protocole (867 KB)