Start-up
The “Start-up” milestone indicates when the line is ready to proceed with the “contractual main format ramp-up” phase.
The line/equipment is able to produce saleable product.
The warranty period starts with the sellable production.
Conditions to be fulfilled to start the ramp-up:
- Static/Dynamic testing have been properly completed
- Maintenance and Operator staff is trained and accredited
- Customer Product relevant parameters (i.e. laboratory check of beverage) are o.k.
- The line/equipment is ready to operate under “sealable” conditions (not with contractual efficiency)
- The customer can produce and sale product (commercial usage of equipment) within the ramp-up schedule
- Operators available
- Raw materials within specification
- Agreed Ramp-Up Schedule (Product mix, Targeted production, number of shifts)