Glossary Performance

Please use "Ctrl F" (Search function) or enter the term you are looking for within the button "Search" and confirm with enter.
A  B  C  D  E  F  G  H  I  J  K  L  M  N  O  P  Q  R  S  T  U  V  W  X  Y  Z 
EnglishGermanFrenchDefinition
C
CustomerKäuferClient It is the organization that has specified, purchased, received and operates the line.
D
Design SpeedNennausbringungCadence Nominal Is the line speed, dedicated to a defined production program, according to the operation conditions (product, container size, temperature, etc.) that is specified in the sales contract between the Buyer and the Supplier.
Qn
E
Effective SpeedEffektivausbringungCadence Effective The quantity produced (Prod) during the Test Time divided by the Gross Time.
Qeff=Prod/tGross
External Down TimesAnlagefremde StörzeitenArrêts Externes Is the sum of the time periods when the leading machine of the line is stopped or set at reduced speed due to failures of equipment, manpower, organization that are not part of the scope or beyond the responsibility of the Supplier.
text
G
Gross TimeAllgemeine LaufzeitTemps Requis Is the sum of the Running Time and the Own down times.
tGross
L
Leading MachineLeitmaschine Machine Critique Is the slower machine from a line in a given environment (container and packaging size, product flow, etc…)
Line AvailabilityWirkungsgrad der AnlageFiabilité de la Ligne The ratio of the effective speed to the set speed. It is the percentage of real production compared to the real line production potential. It is the measurement of the impact of the own failures of the sold equipment on the production. η=Qeff/Qest
Line EfficiencyLiefergrad der AnlageEfficacité de la Ligne The ratio of the effective speed divided by the design speed. It is the percentage or real production compared to the sold line production potential. It is therefore the measurement of the achievement of the contract between the Buyer and the Supplier.
λ=Qeff/Qn
Line Own Down TimesAnlagebedingte StörzeitenArrêts Propres Sum of the time periods when the leading machine is not producing due to a failure of itself or of one of the equipment belonging to the line and part of the Supplier scope.
town
P
Production Time / Test PeriodBetriebszeit/ VersuchszeitTemps de Service / Durée du Test Is the time during which the line is supposed to produce according to the production plan and the agreed test period. Priming and emptying periods of the line must no be part of the test period.
ttot
R
Running timeEffektive LaufzeitTemps de Fonctionnement Sum of the time periods when the leading machine is trouble free functioning. Time periods where the leading machine is slowed down, will be proportionally counted
tRun
S
Set SpeedEinstellausbringungCadence Réelle Is the real amount of products produced during a time unit of trouble free function of the leading machine.
Qest
SupplierLieferantFournisseur Is the organization that has designed, supplied and installed the line.