Duration

Procedure for a stand alone equipment

  • 8 hours of measure with at least 6 hours of Gross Time (tGross) – meaning no more than 25% line external down times (DIN 8783) –is recommended to establish the equipment efficiency.
  • It will be considered successful if, for one 8 hour period, the stand alone equipment efficiency exceeds X% (value to be previously agreed between the parties) based on the design speed.
  • Would the measured efficiency be less than the guaranteed efficiency, the performance test will be considered as failed and a new test be conducted.

Procedure for a complete line acceptance

  • For the contractual main format 8 hours of measurement with at least 6 hours of Gross Time (tGross) – meaning no more than 25% line external down times (DIN 8783) – is recommended by ABMI to establish the Line efficiency.
  • If required, test duration for the contractual main format can be extended to a max of three (3) 8 hours Acceptance Tests to be conducted within 5 consecutive days of same production (Contractual main format).
  • The 8 hours period starts only after the line has been fully primed and reached a stable running order. The line must not be emptied before the performance test data acquisition is terminated.
  • The test will be considered successful if, for the one 8 hour period, the line efficiency exceeds X% (value to be previously agreed between the parties) based on the design speed. Should the test be extended to a max of (3) 8 hours periods, the test will be considered successful if the overall efficiency, over the (3) maximum periods, exceeds X%.
  • If “Acceptance Tests” are to be conducted on more than one format. 8 hours of measurement with at least 6 hours of Gross Time (tGross) is recommended by ABMI  to establish the line efficiency on the specified (contract) additional formats.